Weekly Coordination Meeting Pack

Agenda, attendance, minutes, decisions, and action follow-through for project UTR-26-017. Meeting date: October 13, 2026.

Portfolio reconstruction: This is a fictional meeting built from the current case-study registers. It demonstrates meeting-control practice, not a transcript or record from an employer, client, agency, contractor, or class team.

Meeting control

Record information

MeetingWeekly Project Coordination 09
Date and timeOctober 13, 2026, 10:00 to 11:00 a.m.
LocationHybrid, project office and video conference
Prepared byProject Coordinator
Minutes statusDraft issued October 13, 2026
Correction deadlineOctober 15, 2026 at noon

Meeting objective

Purpose and decision needs

The meeting focuses on items that require coordinated review or a clear next action before the Phase 1 demolition milestone. Routine status is provided as pre-read material so meeting time is reserved for exceptions, dependencies, and decisions.

Decision needed

Concealed corrosion

Confirm the temporary work hold and the date for written technical disposition.

Control confirmation

Pay Application 002

Confirm that the invoice remains unrouted until required support is complete.

Direction needed

PCN-003 quotation

Confirm required cost detail and the resubmission deadline.

Attendance

Participants and represented authority

RoleStatusMeeting responsibilityAuthority represented
Project ManagerPresentChair, delivery and commercial coordinationProject-level routing and recommendations
Construction ManagerPresentField status, sequencing, safety, and qualityField administration within delegated authority
Structural EngineerPresentConcealed condition and technical dispositionTechnical recommendation and written design direction
Finance AnalystPresentCommitment and invoice completenessFinancial verification and routing
General Contractor Project ManagerPresentQuotation, schedule, submittals, and field commitmentsContractor certification of submitted information
General Contractor SuperintendentPresentCurrent work, access, and field constraintsContractor field execution
Project CoordinatorPresentAgenda, records, action tracking, and follow-upNo independent technical, commercial, or payment approval

Pre-read

Records issued before the meeting

Status

Weekly dashboard

Status date October 9, 2026, including schedule, changes, invoices, risks, and closeout.

Open dashboard →
Technical

RFI-027 summary

Concealed corrosion at two support seats and requested written technical direction.

Synthetic record reference
Commercial

PCN-002 quotation

$74,500 and eight calendar days, pending technical scope confirmation and cost review.

Open change log →
Schedule

SCH-006 update request

Integrate the approved five-day PCN-001 impact and show recovery options.

Synthetic record reference
Closeout

CL-001 turnover matrix

Current warranty, as-built, O&M, punch-list, financial, and archive requirements.

Open checklist →

Agenda

Time-boxed discussion plan

TimeTopicLeadIntended output
10:00Safety moment, site access, and current field statusConstruction ManagerConfirm current controls and immediate constraints
10:08Phase 1 milestone and schedule updateGeneral ContractorConfirm forecast, dependencies, and required recovery analysis
10:18RFI-027 concealed corrosionStructural EngineerConfirm work boundary and technical disposition date
10:30PCN-002 and PCN-003 commercial statusProject ManagerDefine review sequence and missing quotation support
10:42Pay Application 002Finance AnalystConfirm administrative hold and missing documents
10:49Closeout readiness and turnover matrixProject CoordinatorConfirm tracking baseline and current owners
10:55Decision recap, action owners, and due datesProject CoordinatorRead back decisions and confirm accountable follow-up

Minutes

Discussion and outcome record

1. Safety, access, and active work

The Construction Manager reported no recordable incidents since the prior meeting. Approved pedestrian phasing under PCN-001 is in use. The next work-zone shift may not occur until the revised routing plan is accepted. Transit operations remain active and unaffected work may continue within the approved sequence.

Record outcome: No new safety decision. A-044 remains open for the revised pedestrian routing plan.

2. Phase 1 milestone and schedule

The General Contractor confirmed that unaffected demolition can continue, but the October 16 Phase 1 milestone remains at risk because work at two support seats is on hold. The approved five-day PCN-001 impact has not yet been incorporated into the current schedule update.

Record outcome: The contractor scheduler will issue SCH-006 by October 14 with the approved impact, the concealed-condition constraint, and available recovery options.

3. RFI-027 concealed corrosion

The Structural Engineer confirmed that the two affected support seats require a written repair detail. Visual observations are not sufficient authority to proceed. The Engineer expects to issue the technical disposition by October 14. The Construction Manager directed the contractor to preserve the affected condition and continue only work that does not disturb the two seats.

Decision D-014: Maintain the technical hold at the two affected support seats until written direction is issued. Unaffected work may continue under the approved sequence.

4. PCN-002 concealed-condition quotation

The $74,500 quotation and eight-day schedule request cannot be fully evaluated until the repair detail defines the work. Finance identified equipment hours and subcontractor backup that will require clarification after the technical scope is confirmed.

Decision D-015: PCN-002 remains a potential change and is not approved. Technical scope confirmation precedes commercial and schedule evaluation.

5. PCN-003 night-work mitigation

The quotation identifies a total of $21,200 but does not separate labor, equipment, monitoring services, and subcontractor support. The Owner has not confirmed that the proposed night shifts are required.

Decision D-016: Return PCN-003 for a detailed breakdown and narrative of the assumed night-work requirement. Resubmission is due October 15.

6. Pay Application 002

The Finance Analyst confirmed that the arithmetic aligns with the current invoice tracker, but certified payroll and the conditional lien release remain missing. The Project Manager stated that incomplete support should not move forward for payment approval.

Decision D-017: PA-002 remains on administrative hold. The coordinator will route it only after the missing records are received and the completeness check is updated.

7. Closeout readiness

The Project Coordinator presented the CL-001 turnover matrix. Participants confirmed the listed categories and current owners. The matrix is a tracking baseline, not evidence that requirements have been accepted or completed.

Decision D-018: Use CL-001 Rev. 0 as the current closeout tracking baseline. Authorized reviewers retain acceptance authority for each final deliverable.

Decision record

Decisions confirmed during read-back

IDDecisionAuthorityEffective dateRelated recordsControl note
D-014Maintain technical hold at two affected support seats; allow unaffected work to continue.Construction Manager following Structural Engineer recommendationOct 13, 2026RFI-027, A-041No field release until written technical direction
D-015Keep PCN-002 in potential-change status until technical scope is confirmed.Project ManagerOct 13, 2026PCN-002, RFI-027No cost or time approval represented
D-016Return PCN-003 for cost detail and confirmation of the night-work basis.Project ManagerOct 13, 2026PCN-003Resubmission does not imply approval
D-017Keep PA-002 on administrative hold until missing support is received.Project Manager and Finance AnalystOct 13, 2026PA-002, A-043Payment approval remains with authorized personnel
D-018Use CL-001 Rev. 0 as the closeout tracking baseline.Project ManagerOct 13, 2026CL-001Tracking baseline is not final acceptance

The same controlled record is available as a plain-text decision log.

Follow-through

Updated actions and deadlines

ActionOwnerDueStatus after meetingCoordinator follow-up
A-041: Issue written repair detail for affected support seatsStructural EngineerOct 14OpenConfirm issue and route to field team
A-042: Review PCN-002 after technical scope is confirmedProject ManagerOct 16BlockedVerify quote backup before review meeting
A-043: Submit certified payroll and conditional lien releaseGeneral ContractorOct 14Overdue, revisedSend final completeness notice
A-044: Submit revised pedestrian routing planGeneral ContractorOct 14In progressRoute upon receipt to Construction Manager
A-045: Issue SCH-006 with impacts and recovery optionsGeneral Contractor SchedulerOct 14In progressCompare forecast to Oct 16 milestone
A-047: Resubmit PCN-003 detailed breakdownGeneral ContractorOct 15NewCheck labor, equipment, subcontractor, and assumption detail
A-048: Circulate draft minutes and collect correctionsProject CoordinatorOct 15In progressPublish final after correction window

Quality checks

Meeting record controls demonstrated

  • Routine status is separated from items requiring meeting time.
  • Discussion, decisions, and actions are recorded as different types of information.
  • Every decision names the authority and states what it does not authorize.
  • Every action has one owner, due date, related record, and coordinator follow-up.
  • Minutes include a correction window before final publication.
  • Technical, commercial, financial, and administrative completeness are not treated as the same approval.