Source and identity
PCN-002 is tied to RFI-027, field observations, structural details, and one consistent change title.
Inspectable evidence | Synthetic data
PCN-002, concealed corrosion at support seats. This artifact shows how a coordinator can verify that a proposed change is complete enough for authorized technical, commercial, schedule, and owner review.
Routing gates
The checklist is organized by the type of review the package must support. A complete administrative package does not mean the change is valid or approved.
PCN-002 is tied to RFI-027, field observations, structural details, and one consistent change title.
The contractor quotation is present, but its proposed scope must be reconciled to the Structural Engineer's written disposition.
Labor, material, equipment, subcontractor backup, and an eight-day time-impact narrative are included for authorized review.
The package identifies a possible pedestrian-control impact, but the Construction Manager must confirm whether a revised plan is required.
Technical, project, finance, schedule, and owner reviewers are identified. The coordinator is not listed as an approver.
Commitment, schedule, decision, invoice, and closeout records are updated only after written authorization is received.
Completeness matrix
The table highlights what the coordinator can verify, what remains unresolved, who owns the next step, and which review gate is affected.
| Requirement | Evidence | Status | Routing gate | Owner and next action |
|---|---|---|---|---|
| Source condition | RFI-027 and field observation record | Complete | Technical review | Structural Engineer to issue disposition by Oct 13 |
| Proposed work scope | Quotation Q-118 Rev 1 | Needs review | Technical review | Confirm quotation matches the engineer's direction |
| Cost breakdown | Labor, material, equipment, and subcontractor backup | Complete | Commercial review | Finance Analyst to verify arithmetic and exclusions by Oct 14 |
| Schedule impact | Eight-day narrative and affected activities | Complete | Schedule review | Project Manager to validate logic and recovery options |
| Safety and access impact | Pedestrian-control note | Clarify | Construction review | Construction Manager to confirm plan requirements by Oct 12 |
| Funding reference | Commitment register and contingency summary | Complete | Commercial review | Project Manager to confirm available contingency |
| Final disposition | Written approval, rejection, or return | Not started | Owner decision | Coordinator records the authorized outcome when issued |
The downloadable CSV contains the detailed verification fields, owners, due dates, routing gates, and coordinator notes.